Construction of 100TPD Sulphuric acid plant and 6 TPD SO2 Plant for M/s Sable Zinc at Kabwe, Zambia.
Client: M/s Sable Zinc (Metorex Group), Kabwe, Zambia
Process Licensor: Outotec
Consultant: Furnace Fabrica (India) Ltd..
Scope:
- Complete fabrication and erection of Mechanical, Electrical and Instrumentation including piping, ducting and technological structures.
- Structural: 50 MT
- Equipment fabrication and erection: 500 MT
- All Electrical and Instrumentation erection and commissioning
- Refractory supply and Application: 400 MT
- External Insulation : 450 M2
Year of Execution: 2006 - 2007
|
|
|
 |
|